NR NR/SMS/PART/D ISSUE 8 Signal Maintenance Specifications (SMS): Level Crossing Annual Test - Compliance Date: 31 May 2017

Список продуктов
Данный раздел/документ содержится в продуктах:

 

Network Rail

Signal Maintenance Specifications (SMS): Level Crossing Annual Test - Compliance Date: 31 May 2017
 N NR/SMS/PART/D ISSUE 8

 

Annotation

 

GENERAL

This test plan is the ‘Service B Tests’ of NR/SMS/LC10 and NR/SMS/Test/070. It is for use of the person conducting the annual test of the level crossing and has relevant ‘tick boxes’ by each task so that particular item of the test can be correctly recorded as per the index in ‘crossing defects’.

It does not cover AHBC installations controlled by HXP-3 crossing processors The numbering of the sections in this test plan is unique; they do not follow on from the operation sequence test in NR/SMS/Test/070 ‘Service A Tests’.

To perform the annual test the following documents will be required:

• The crossing ground plan

• The level crossing order

• The crossing control tables

• The signalling plan

Missing documentation shall be listed as a defect.

 

Автоматический перевод:

 

Signal Maintenance Specifications (SMS): железнодорожный переезд ежегодный тест - дата соответствия: 31 мая 2017

ОБЩИЙ

Этот план проведения испытаний является ‘Сервисными Тестами B’ NR/SMS/LC10 и NR/SMS/Test/070. Это для использования лица, проводящего ежегодный тест железнодорожного переезда, и имеет соответствующие ‘поля галочки’ каждой задачей так, чтобы конкретный элемент теста мог быть правильно зарегистрирован согласно индексу в ‘пересечении дефектов’.