CEI CLC/TS 50549-2 Requirements for the connection of a generating plant to a distribution system Part 2: Connection to a MV distribution system
Данный раздел/документ содержится в продуктах:
- Техэксперт: Машиностроительный комплекс
- Картотека зарубежных и международных стандартов
- IEC 60079-11 CORR 1 Explosive atmospheres – Part 11: Equipment protection by intrinsic safety “I” - Edition 6.0
- 29
- IEC 60079-11 CORR 1 Explosive atmospheres – Part 11: Equipment protection by intrinsic safety “I” - Edition 6.0
- 29.260
- IEC 60079-11 CORR 1 Explosive atmospheres – Part 11: Equipment protection by intrinsic safety “I” - Edition 6.0
- 29.260.20
- BSI BS EN 60079-10-1 Explosive atmospheres - Part 10-1: Classification of areas - Explosive gas atmospheres
- CENELEC EN 60079-0 Explosive atmospheres - Part 0: Equipment - General requirements - Incorporates Amendment A11: 2013
- BSI BS EN 60079-6 Explosive atmospheres - Part 6: Equipment protection by oil immersion “o” - AMD: June 30, 2008
- BSI BS EN 13922 Tanks for transport of dangerous goods - Service equipment for tanks - Overfill prevention systems for liquid fuels
- Картотека зарубежных и международных стандартов
Comitato Elettrotecnico Italiano
Requirements for the connection of a generating plant to a distribution system Part 2: Connection to a MV distribution system
N CLC/TS 50549-2
Annotation
The purpose of this Technical Specification is to provide technical guidance on the requirements for generating plants which can be operated in parallel with a distribution network.
For practical reasons, this Technical Specification refers to the distribution system operator in case settings have to be defined and/or provided, even when these settings are to be defined and/or provided by another actor according to national and European legal framework.
NOTE 1 This includes European network codes and their national implementation, as well as further national regulations.
NOTE 2 Further national requirements especially for the connection to the distribution network and the operation of the generating plant can apply.
The requirements of this Technical Specification apply to all generating plants, electrical machinery and electronic equipment, irrespective of the kind of primary energy source and irrespective of the presence of loads in the producer’s network that meet all of the following conditions:
– converting any primary energy source into AC electricity;
– connected to a MV distribution network;
– intended to operate in parallel with this distribution network under normal network operating conditions.
NOTE 3 Generating plants connected to a LV distribution network fall into the scope of EN 50438 (up to 16 A) and CLC/TS 50549-1 (above 16 A).